Bankers Petroleum’s 2010 average production increased 49% to 9,597 bopd from 6,438 bopd in 2009. The company increased production through annual capital investment in Albania, of US$122 million, which includes the effective implementation of the Patos-Marinza development plan as well as applying EOR and secondary extraction techniques to increase the field's recoverable reserves.
Bankers Petroleum 2011 capital program budgeted at US$ 215 million and projected 2012-2014 capital programs to average $200mm/year.
As part of 2011, the company plan to drill 66 horizontal and vertical wells and complete 120 well reactivations and work-overs at the Patos-Marinza oilfield to increase production facilities to handle our target exit production rate of 20,000 bopd